Millville

"A Beautiful Way of Life"

Anticipated Construction Schedule & Associated Lane Closures

Date Posted: Wednesday, June 18th, 2014

Below is an outline of the anticipated construction schedule and associated lane closures for work on and within the SR 26 Widening Project during the next week.

Monday, July 18, 2016m through Thursday, July 21, 2016 – Night Shift

Begin final paving activities on Route 26 between the Assawoman Canal and Central Avenue. Motorists should anticipate eastbound and westbound lane closures on Route 26 between the Assowaman Canal and Central Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel and Law Enforcement from 9:00 PM to 8:00 AM.

Monday, July 18, 2016, through Thursday, July 21, 2016 – Dayshift

Continue grading for new curb and sidewalk on Central Avenue between Route 26 and Woodland Avenue. Motorists should anticipate northbound lane closures on Central Avenue between Woodland Avenue and Route 26 with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 AM to 5:00 PM.

Complete adjusting manholes and grading for swale ditches along Route 26 between Roxana Road and Powell Farm Road. Motorists should anticipate eastbound or westbound lane shifts on Route 26 at between Old Mill Road and Powell Farm Road with both lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00 AM to 5:00 PM.

Tags: , ,