Anticipated Construction Schedule

Date Posted: Monday, June 16th, 2014

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next two weeks.

Monday June 16, 2014 – Friday June 20, 2014:

Continue reconstruction of the Central Avenue/SR 26 intersection.  Motorists should anticipate eastbound or westbound lane closures on SR 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM as well as lane closures on Central Avenue at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

Continue reconstruction of the Old Mill Road/SR 26 intersection.  Motorists should anticipate   lane closures at Old Mill Road and SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

Continue work on the installation of the new drainage system between Cedar Drive and Old School Lane.  Motorists should anticipate the eastbound or westbound lane of SR 26 between Old Mill Road and Old School Lane to be closed with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM.

Continue excavation of Storm Water Management Pond #332 located east of SR 17 (Roxana Road) during the day.  No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #331 located west of Irons Lane.  No lane closures are anticipated for this work.

 

Monday June 23, 2014 – Friday June 27, 2014:

Continue reconstruction of the Old Mill Road/SR 26 intersection. Motorists should anticipate lane closures at Old Mill Road and SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

Continue work on the installation of the new drainage system between Grants Avenue and Woodland Avenue. Motorists should anticipate the eastbound or westbound lane of SR 26 between Old Mill Road and Woodland Avenue to be closed with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM.

Continue excavation of Storm Water Management Pond #332 located east of SR 17 (Roxana Road) during the day. No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #331 located west of Irons Lane. No lane closures are anticipated for this work.

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next two weeks. Monday June 9, 2014 through Friday June 13, 2014Begin reconstruction of the Central Avenue/SR 26 intersection. Motorists should anticipate eastbound or westbound lane closures on SR 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM as well as lane closures on Central Avenue at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.Continue reconstruction of the Old Mill Road/SR 26 intersection. Motorists should anticipate lane closures on Old Mill Road at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.
Continue work on the installation of the new drainage system between Old Mill Road and Old School Lane. Motorists should anticipate the eastbound or westbound lane of SR 26 between Old Mill Road and Old School Lane to be closed with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM.

Monday June 16, 2014 – Friday June 20, 2014:

Continue reconstruction of the Central Avenue/ SR 26 intersection. Motorists should anticipate eastbound or westbound lane closures on SR 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM as well as lane closures on Central Avenue at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

Continue reconstruction of the Old Mill Road/SR 26 intersection. Motorists should anticipate lane closures on Old Mill Road at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

Continue work on the installation of the new drainage system between Grants Avenue and Woodland Avenue. Motorists should anticipate the eastbound or westbound lane of SR 26 between Old Mill Road and Woodland Avenue to be closed with traffic alternating through the work zone utilizing a flagging operation between 07:00PM and 6:00AM.

Continue excavation of Storm Water Management Pond #332 located east of SR 17 (Roxana Road). No lane closures are anticipated for this work.